Rates, budgets and profitability

How to measure project profitability

Project margin and markup formulas, labor cost from timesheets, subcontractors, expenses, discounts, write-offs, forecasts and client profitability.

Updated · 4 min read · 10 questions answered

Short answer

Project margin is (revenue − costs) ÷ revenue. Labor cost comes from timesheets: each person's hours times their cost rate. Include subcontractors as costs, decide once how to treat pass-through expenses, and use the revenue you actually realize after discounts and write-offs. Unbilled hours still cost money. For in-flight projects, estimate the final cost from actual cost plus a re-estimate of the remaining work, and calculate client profitability from summed revenue and costs rather than averaging project margins.

The core formulas

What is the formula for project profit margin?

Link to this answer: What is the formula for project profit margin?

Subtract project costs from project revenue, then divide by revenue.

Formula

Project margin

project margin % = (revenue − project costs) ÷ revenue × 100

A project with revenue of 20,000 and costs of 13,000 has a profit of 7,000 and a margin of 7,000 ÷ 20,000 = 35%. "Costs" here are direct project costs: labor from timesheets, subcontractors and direct expenses. Add overhead only if you want a fully loaded margin, and label it.

What is the difference between project margin and markup?

Link to this answer: What is the difference between project margin and markup?

Margin divides profit by revenue; markup divides profit by cost. The same project gives two different percentages.

Worked example

Same project, two percentages

Revenue 20,000, costs 13,000, profit 7,000. Margin = 7,000 ÷ 20,000 = 35%. Markup = 7,000 ÷ 13,000 = 53.8%.

To hit a target margin, price at cost ÷ (1 − margin). A 35% margin on 13,000 of costs needs revenue of 13,000 ÷ 0.65 = 20,000. Pricing at cost + 35% (17,550) gives only a 25.9% margin, which is a common quoting mistake.

How do I calculate labor cost from project timesheets?

Link to this answer: How do I calculate labor cost from project timesheets?

Multiply each person's hours on the project by their cost rate for the period, then add them up. For a team of three: 20 hours × 80 + 45 hours × 54 + 30 hours × 35 = 5,080. See costing mixed teams.

Include all hours recorded on the project, billable and non-billable. Non-billable time on a project is still a cost of delivering it.

What goes into revenue and cost

Should project margin include subcontractor costs?

Link to this answer: Should project margin include subcontractor costs?

Yes. Freelancers and subcontractors working on the project are direct costs, just like staff time. Leaving them out makes heavily outsourced projects look far more profitable than they are.

If you mark up subcontracted work, the margin calculation captures that automatically: their cost is in costs and what you bill for their work is in revenue.

Should reimbursed expenses count as project revenue?

Link to this answer: Should reimbursed expenses count as project revenue?

Choose one consistent method and say which you use. Either exclude pass-through expenses from both revenue and costs, or include them in both. The profit is the same; the margin percentage is not.

Worked example

The same project, two treatments

Fees 20,000, labor and subcontractor costs 13,000, plus 5,000 of travel re-billed at cost. Excluding the travel: margin 7,000 ÷ 20,000 = 35%. Including it in both: margin 7,000 ÷ 25,000 = 28%.

Excluding pass-through costs usually gives a fairer comparison between projects with and without large expenses.

How do client discounts affect project margin?

Link to this answer: How do client discounts affect project margin?

A discount reduces revenue while costs stay the same, so the whole discount comes out of profit. A 10% discount on 20,000 cuts revenue to 18,000; with 13,000 of costs, margin falls from 35% to 5,000 ÷ 18,000 = 27.8%.

Record the full price and the discount separately rather than only the net amount. That shows how much margin you are giving away across clients.

How do unbilled hours affect hourly project profitability?

Link to this answer: How do unbilled hours affect hourly project profitability?

They add cost without adding revenue. On an hourly project, every hour you work but do not bill is pure cost.

If a project bills 150 hours at 120 (18,000) and the team also worked 30 unbilled hours, the labor cost covers all 180 hours. At a blended cost of 55, labor is 9,900 and the margin is (18,000 − 9,900) ÷ 18,000 = 45%. Had all 180 hours been billed, revenue would be 21,600 and the margin 54.2%.

How do write-offs affect realized project revenue?

Link to this answer: How do write-offs affect realized project revenue?

A write-off removes billed or billable value you do not collect, so realized revenue is the original amount minus the write-off. If 18,000 was invoiced and 1,800 is written off, realized revenue is 16,200.

Calculate margin on realized revenue, not on the invoice. Track write-offs by client and reason: repeated write-offs on one client usually point to scope or relationship problems. The ratio of realized to standard value is realization.

Projects in progress and clients

How can I estimate profitability before a project is finished?

Link to this answer: How can I estimate profitability before a project is finished?

Forecast the final cost: the cost so far plus a fresh estimate of the remaining work. Compare it with expected revenue.

Worked example

A mid-project forecast

Fee 24,000. Cost to date 9,000 (165 hours). The team re-estimates 110 hours to finish at a blended cost of 55, which is 6,050. Forecast cost is 15,050 and forecast margin is (24,000 − 15,050) ÷ 24,000 = 37.3%.

Re-estimate the remaining work from what is left to do, not from the original budget minus hours used; the original budget is what you are checking. Repeat the forecast at each milestone. See budget used versus progress.

How do I calculate profitability across all projects for one client?

Link to this answer: How do I calculate profitability across all projects for one client?

Add up revenue across the client's projects, add up their costs, and calculate one margin from the totals. Do not average the project margins, because a small project with an extreme margin will distort the result.

ProjectRevenueCostsMargin
Website40,00030,00025%
Monthly SEO12,0006,00050%
Client total52,00036,00030.8%

The simple average of 25% and 50% is 37.5%, but the client actually yields 16,000 ÷ 52,000 = 30.8%. Include non-billable time spent on the account, such as account management, in the client's costs.

Put the answers to work
on tomorrow’s timesheet.

Try Wrap with your own team. Free for up to 10 active members.