Two different rates
What is the difference between an employee cost rate and a billing rate?
Link to this answer: What is the difference between an employee cost rate and a billing rate?A cost rate is your internal cost for one hour of a person's time. A billing rate is the price per hour you charge a client. The difference between them, multiplied by hours, is the gross profit on that time.
| Cost rate | Billing rate | |
|---|---|---|
| Who sees it | Finance, owners | The client, on quotes and invoices |
| Based on | Salary, employer costs, available hours | Market, value, role, client agreement |
| Used for | Project cost and margin | Revenue and invoices |
| Example | 53.51 per hour | 120 per hour |
Keep cost rates restricted. Most team members need to record time without seeing what colleagues cost.
How do I convert an annual salary into an hourly cost?
Link to this answer: How do I convert an annual salary into an hourly cost?Add employer costs to the salary, then divide by the hours the person is actually available for work.
Worked example
From salary to loaded hourly cost
Salary 78,000. Employer payroll taxes, pension and benefits are assumed at 18%, which adds 14,040, for a total of 92,040. Contracted hours are 40 × 52 = 2,080, minus 25 days of leave and 8 public holidays (264 hours) and an allowance of 96 hours for sickness and training, giving 1,720 available hours. Loaded cost rate: 92,040 ÷ 1,720 = 53.51 per hour.
Dividing the salary by 2,080 alone (78,000 ÷ 2,080 = 37.50) gives the pay rate. It understates cost because it ignores employer costs and the hours that are paid but not worked. The 18% and the hour allowances here are illustrative; use your own payroll figures.
Should employer benefits be included in hourly employee cost?
Link to this answer: Should employer benefits be included in hourly employee cost?Yes, for any cost rate used to judge project profitability. Employer payroll taxes, pension contributions, health insurance and similar benefits are part of what the hour costs you.
Leave out costs that are not tied to employment, such as office rent and software. Those are overhead; see overhead in labor costs.
Should paid leave be included in hourly employee cost?
Link to this answer: Should paid leave be included in hourly employee cost?Yes, but only once. The usual way is to keep the full salary in the numerator and divide by available hours (after leave and holidays), as in the example above. That spreads the cost of paid leave across the hours that are worked.
Do not also add leave pay as a separate cost. That counts it twice and overstates the rate.
Should overhead be included in project labor costs?
Link to this answer: Should overhead be included in project labor costs?Report it as a separate layer. Direct labor cost (salary plus employer costs) shows the margin a project contributes; fully loaded cost (adding a share of rent, software, management and admin) shows whether it covers the business.
Worked example
Two layers of cost
Overhead of 300,000 a year spread over 15,000 available team hours adds 20 per hour. A person with a 53.51 direct cost rate has a fully loaded rate of 73.51. A project billed at 90 an hour has a positive contribution per hour (36.49) and a smaller fully loaded margin (16.49).
Mixing the two in one number makes it hard to tell a project that loses money from one that simply carries its share of overhead.
Contractors and mixed teams
How do I calculate project cost for an hourly contractor?
Link to this answer: How do I calculate project cost for an hourly contractor?Multiply the hours they worked on the project by their hourly rate, and add any agreed fees or expenses. A contractor paid 70 an hour for 30 hours costs 2,100.
There is no need to load employer costs, since you pay none, but make sure the contractor's hours are recorded against the project like everyone else's. If the contractor works for a fixed fee, record the fee as a direct project cost and track their hours for effort reporting.
How do I cost a project staffed by people with different salaries?
Link to this answer: How do I cost a project staffed by people with different salaries?Multiply each person's hours by their own cost rate and add the results. Do not use an average rate unless that is all you have.
Worked example
A three-person project
| Person | Hours | Cost rate | Cost |
|---|---|---|---|
| Senior strategist | 20 | 80 | 1,600 |
| Designer | 45 | 54 | 2,430 |
| Junior designer | 30 | 35 | 1,050 |
| Total | 95 | 5,080 |
The blended cost rate is 5,080 ÷ 95 = 53.47 per hour, but only because of this particular mix. A different mix changes it.
Should project cost reports use historical or current employee rates?
Link to this answer: Should project cost reports use historical or current employee rates?Use the rate that applied on the date the work was done for actual costs, and current rates for estimates and forecasts. If someone's cost rate rises in July, their March hours should still be costed at the March rate.
That needs cost rates with effective dates. Recalculating past work at today's rates rewrites the history of what projects actually cost and makes month-to-month comparisons meaningless.
Billing rate structures
How do I set different billing rates for the same person?
Link to this answer: How do I set different billing rates for the same person?Attach rates to the work rather than only to the person. Common layers are a default rate per role, an override per client, and an override per project or phase. The most specific rate wins: a phase rate beats a client rate, which beats the role default.
Write down the precedence rule and keep rates in one place, not typed into individual entries. Otherwise the same hour can be priced differently depending on who entered it.
Should junior and senior staff have different client billing rates?
Link to this answer: Should junior and senior staff have different client billing rates?It is common and usually fair: clients pay more for experience, and you pay more for it. The alternative is a single blended rate for the team, which is simpler to quote and hides who did the work.
Each has a risk. Role-based rates encourage clients to ask for the cheapest person; a blended rate can lose money if the mix shifts towards senior staff. Whichever you choose, check the effective hourly rate against costs periodically.