Setting the budget
How do I turn a project fee into an hours budget?
Link to this answer: How do I turn a project fee into an hours budget?Divide the fee by the hourly rate you planned to earn, then hold back a contingency.
Worked example
From fee to working budget
A 24,000 fee priced at a blended 120 an hour supports 24,000 ÷ 120 = 200 hours. Holding back 10% as contingency leaves a working budget of 180 hours for the team, with 20 hours in reserve.
If you priced from cost and a target margin instead, use that same rate. The budget should match the assumption behind the price, otherwise the budget and the quote disagree from day one.
How do I allocate an hours budget across project phases?
Link to this answer: How do I allocate an hours budget across project phases?Split it by your estimate of each phase's effort, based on similar past projects where you have them.
| Phase | Share | Hours (of 180) |
|---|---|---|
| Discovery | 15% | 27 |
| Design | 35% | 63 |
| Build | 35% | 63 |
| Launch and handover | 15% | 27 |
Track time against each phase so you can see which one runs over while there is still time to act. Your own history beats any template: after a few projects, compare actual splits with these shares and adjust.
How do I calculate the percentage of a project budget used?
Link to this answer: How do I calculate the percentage of a project budget used?Divide the hours recorded so far by the budgeted hours, times 100. 117 hours used of a 180-hour budget is 117 ÷ 180 = 65%.
Do this per phase as well as for the whole project. A project at 65% overall can hide a design phase at 110%.
How do I compare budget used with deliverables completed?
Link to this answer: How do I compare budget used with deliverables completed?Estimate the percentage of work complete for each phase, then compare it with the percentage of budget used. Progress should be judged from deliverables (approved, done, remaining), not from hours.
Worked example
Burn versus progress
Design has used 54 of 63 hours (86%) but only two of four page templates are approved (about 50% complete). At this pace, design will need roughly 54 ÷ 0.5 = 108 hours, 45 more than budgeted.
That forecast (hours so far ÷ fraction complete) is crude but useful early. Check it against the team's own estimate of what is left.
Recognizing scope creep
What is the difference between scope creep and an approved scope change?
Link to this answer: What is the difference between scope creep and an approved scope change?Scope creep is extra work that enters the project without being agreed, priced or scheduled. An approved scope change is the same kind of extra work after the client has accepted its cost and timing, usually in a written change order.
The work can be identical; what differs is the agreement. The aim is not to refuse every request but to turn creep into approved changes.
How do I spot scope creep in timesheet data?
Link to this answer: How do I spot scope creep in timesheet data?Look for hours on work the scope does not mention, extra revision rounds and phases that keep growing after approval. Typical patterns:
- Hours on tasks or deliverables that are not in the statement of work.
- More revision rounds than the agreement includes.
- A phase whose hours keep growing after its deliverables were approved.
- Many small "quick" entries for one client that add up to a day or more each month.
- Descriptions containing words like "also", "extra", "additional" or "new request".
A weekly report of hours by phase and task, compared with the budget, makes most of these visible.
How should I track work requested beyond the agreed scope?
Link to this answer: How should I track work requested beyond the agreed scope?Record it on the same project, but on a separate task, phase or tag (for example "Change request: Spanish landing page"), with a reference to who asked and when. Start tracking it as soon as the work starts, before anyone has decided whether it will be billed.
That keeps the main budget honest and gives you a precise total for each request. See labelling out-of-scope entries.
Acting on it
When should I alert a client that project hours are running out?
Link to this answer: When should I alert a client that project hours are running out?Early enough that they can still choose. Common practice is to share budget status at regular intervals and send a specific alert at agreed thresholds, for example when 75% of hours are used, and again at 90%.
Put the thresholds in the agreement so alerts are expected rather than alarming. Include what has been delivered, what remains, the forecast to finish, and the options: reduce scope, add budget or change the timeline.
How do I use recorded hours to support a change request?
Link to this answer: How do I use recorded hours to support a change request?Total the hours recorded on out-of-scope work, list them by request with dates and descriptions, and show the effect on the budget.
Worked example
A change request summary
"Since 3 June we have spent 14.5 hours on items outside the original scope: the Spanish landing page (9 hours), two extra banner sizes (3.5 hours) and an additional revision round on the homepage (2 hours). At the agreed rate of 120 that is 1,740. We propose adding 1,740 to the project and 12 further hours for the remaining Spanish pages."
Specific, dated entries are far more persuasive than "we've done a lot of extra work".
How do I update a project budget after a scope change?
Link to this answer: How do I update a project budget after a scope change?Record the approved change as its own budget line (a new phase or a change-order amount) and add it to the total, while keeping the original budget visible. The project then has an original baseline, approved changes and a current budget.
Never quietly overwrite the original number. Keeping both shows how much the project grew and why, which is exactly what you need when pricing the next similar project.